Setup
Master plan setup – Use futures date as requirement date
pl-PO Use Futures date as Requirement date = Yes
pl-PO Use Futures date as Requirement date = No
pl-PO + pl-Prod Use Futures date as Requirement date = No
Coverage group – Action Basis Date
Action Basis date = Requirement date
Action Basis date = Futures date
Test cases
Scenario
Sales order with confirmed delivery date: 16.11.2016; the lead time setup of the purchase item (M0009) doesn’t allow the PO to be on time.
pl-PO Use Futures date as Requirement date = Yes; Action Basis date = Requirement date
pl-PO Use Futures date as Requirement date = Yes; Action Basis date = Futures date
pl-PO Use Futures date as Requirement date = No; Action Basis date = Requirement/Futures date
Note: Changing Action Basis date does not have an affect
pl-PO + pl-Prod Use Futures date as Requirement date = No; Action Basis date = Futures/Requirement date
Note: Changing Action Basis date does not have an affect
Recommendation
USE: Use Futures date as Requirement date = Yes; Action Basis date = Requirement date
With this setting the system tells you what is late and what you should try to do about it.
Источник:
https://thwidmer.wordpress.com/2016/...uirement-date/
__________________
Расскажите о новых и интересных блогах по Microsoft Dynamics, напишите
личное сообщение
администратору.
Blog bot
Посмотреть профиль
Найти ещё сообщения от Blog bot